The measures of the chapter Principles of approximation algorithms, for an algorithm \(\mathscr{A}\) with value \(\mathscr{A}(I)\) on an instance \(I\) of optimal value \(z(I)\):
The worst-case performance ratio is the supremum of the performance ratio (A1) over all the instances:
Exercise 34.1: Performance ratios and errors (1)
A heuristic algorithm \(\mathscr{A}\) for a minimization problem and a heuristic algorithm \(\mathscr{B}\) for a maximization problem give the following values on some instances:
Questions
-
Compute the performance ratio, the additive error and the relative error of \(\mathscr{A}\) on its five instances.
-
Do the same for \(\mathscr{B}\) on its three instances.
-
Using only these data, which of the constants \(\alpha=\frac{7}{5}\) and \(\alpha=\frac{3}{2}\) can be a relative performance guarantee of \(\mathscr{A}\)? What would a proof that \(\mathscr{A}\) is a \(\frac{3}{2}\)-approximation algorithm need?
-
Suppose that \(\mathscr{A}\) is proved to be a \(\frac{3}{2}\)-approximation algorithm. Is the guarantee tight? Give a lower bound on \(r(\mathscr{A})\) and on \(r(\mathscr{B})\).
Solution
We use the definitions (A1)–(A4) of the box at the beginning of the chapter.
-
For a minimization problem the ratio is \(\frac{\mathscr{A}(I)}{z(I)}\):
instance \(\mathscr{A}(I)\) \(z(I)\) ratio additive error relative error \(I_1\) \(12\) \(10\) \(\frac{6}{5}\) \(2\) \(\frac{1}{5}\) \(I_2\) \(9\) \(9\) \(1\) \(0\) \(0\) \(I_3\) \(15\) \(10\) \(\frac{3}{2}\) \(5\) \(\frac{1}{2}\) \(I_4\) \(20\) \(16\) \(\frac{5}{4}\) \(4\) \(\frac{1}{4}\) \(I_5\) \(7\) \(6\) \(\frac{7}{6}\) \(1\) \(\frac{1}{6}\) -
For a maximization problem the ratio is \(\frac{z(I)}{\mathscr{B}(I)}\):
instance \(\mathscr{B}(I)\) \(z(I)\) ratio additive error relative error \(I_1\) \(30\) \(36\) \(\frac{6}{5}\) \(6\) \(\frac{1}{6}\) \(I_2\) \(25\) \(25\) \(1\) \(0\) \(0\) \(I_3\) \(16\) \(24\) \(\frac{3}{2}\) \(8\) \(\frac{1}{3}\) All the ratios are at least \(1\), as they must be for feasible solutions.
-
On \(I_3\) the ratio is \(\frac{3}{2}>\frac{7}{5}\): \(\alpha=\frac{7}{5}\) is not a relative performance guarantee. The data do not exclude \(\alpha=\frac{3}{2}\), since every ratio is at most \(\frac{3}{2}\). A proof must show \(\mathscr{A}(I)\le\frac{3}{2}\,z(I)\) for every instance \(I\): finitely many examples can only disprove a guarantee.
-
Yes: the instance \(I_3\) attains the ratio \(\frac{3}{2}\), so no smaller constant is a guarantee, and \(r(\mathscr{A})=\frac{3}{2}\). Without a proof, the data give only lower bounds: \(r(\mathscr{A})\ge\frac{3}{2}\) and \(r(\mathscr{B})\ge\frac{3}{2}\) (instance \(I_3\) of \(\mathscr{B}\)).
Exercise 34.2: A tight guarantee for a simple algorithm (1)
For \(P\|C_{\max}\) consider the algorithm \(\mathrm{ONE}\), which assigns all the jobs to machine \(1\), so that \(\mathrm{ONE}(I)=\sum_{j\in\mathscr{J}}t_j\). Every instance satisfies \(z(I)\ge\frac{\sum_j t_j}{m}\), since the \(m\) loads sum to \(\sum_j t_j\). Consider the instances
-
\(I_1\): \(m=2\) and \(t=(7,5,4,3,3)\);
-
\(I_2\): \(m=3\) and \(t=(9,2,2,2,1)\);
-
\(I_3\): \(m=3\) and \(t=(5,5,4,4,3,3,3)\);
Questions
-
Compute \(\mathrm{ONE}(I)\), \(z(I)\) (by enumeration) and the performance ratio on the three instances.
-
Prove that \(\mathrm{ONE}\) is an \(m\)-approximation algorithm for every fixed number \(m\) of machines.
-
Build, for every \(m\ge 2\), an instance on which the ratio is exactly \(m\), and check it with \(m=4\). What can you conclude?
-
Does \(\mathrm{ONE}\) have a finite additive performance guarantee? Use the instance \(I_1\) with all the processing times multiplied by \(10\).
Solution
We use the definitions (A1)–(A4) of the box at the beginning of the chapter.
-
instance \(m\) \(\mathrm{ONE}(I)\) \(z(I)\) ratio guarantee \(m\) \(I_1\) \(2\) \(22\) \(11\) \(2\) \(2\) \(I_2\) \(3\) \(16\) \(9\) \(\frac{16}{9}\) \(3\) \(I_3\) \(3\) \(27\) \(9\) \(3\) \(3\) The ratio never exceeds \(m\), and it is equal to \(m\) on \(I_1\) and \(I_3\).
-
For every instance, \(z(I)\ge\frac{\sum_j t_j}{m}\) gives
\[ \frac{\mathrm{ONE}(I)}{z(I)}=\frac{\sum_j t_j}{z(I)}\le\frac{\sum_j t_j}{\frac{\sum_j t_j}{m}}=m . \] -
Take \(n=2m\) jobs of time \(1\). Two jobs per machine give \(z(I)=2\), while \(\mathrm{ONE}(I)=2m\): the ratio is \(m\). With \(m=4\): \(\mathrm{ONE}(I)=8\), \(z(I)=2\) (enumeration) and the ratio is \(4\). The guarantee \(m\) is tight and \(r(\mathrm{ONE})=m\).
-
Multiplying the times of \(I_1\) by \(10\) gives \(t=(70,50,40,30,30)\), with \(\mathrm{ONE}(I)=220\) and \(z(I)=110\): the additive error goes from \(11\) to \(110\). Multiplying by any \(K\) multiplies the error by \(K\), so no constant \(\beta\) bounds it: \(e(\mathrm{ONE})=\infty\), while the ratio stays \(2\).
Exercise 34.3: An algorithm without a guarantee (1)
For the BPP consider the algorithm \(\mathrm{SEP}\), which packs every item in a separate bin, so that \(\mathrm{SEP}(I)=n\). Consider the instance \(I_0\) with \(c=10\) and weights \((6,5,4,3,2)\), and, for \(k\in\Z_{\ge 2}\), the instances \(I_k\) with \(c=k\) and \(2k\) items of weight \(1\).
Questions
-
Compute \(\mathrm{SEP}(I_0)\), \(z(I_0)\), the performance ratio and the additive error on \(I_0\).
-
Compute the performance ratio on \(I_k\) for \(k=3,5,10\) (use enumeration for \(k=3\)), and its expression for every \(k\).
-
Is \(\mathrm{SEP}\) an \(\alpha\)-approximation algorithm for some constant \(\alpha\)? Give \(r(\mathrm{SEP})\) and \(e(\mathrm{SEP})\).
-
Using \(z(I)\ge 2\), show that \(\frac{\mathrm{SEP}(I)}{z(I)}\le\frac{n}{2}\). Why is \(\frac{n}{2}\) not a relative performance guarantee?
Solution
We use the definitions (A1)–(A4) of the box at the beginning of the chapter.
-
\(\mathrm{SEP}(I_0)=5\) and \(z(I_0)=2\) (patterns \(\{1,3\}\) and \(\{2,4,5\}\)). The ratio is \(\frac{5}{2}\) and the additive error is \(5-2=3\).
-
Two bins of capacity \(k\) hold the \(2k\) unit items, and one bin is not enough, so \(z(I_k)=2\):
\(k\) \(c\) \(\mathrm{SEP}(I_k)=2k\) \(z(I_k)\) ratio \(3\) \(3\) \(6\) \(2\) \(3\) \(5\) \(5\) \(10\) \(2\) \(5\) \(10\) \(10\) \(20\) \(2\) \(10\) In general the ratio is \(\frac{2k}{2}=k\).
-
No: for every constant \(\alpha\), the instance \(I_k\) with \(k>\alpha\) has ratio \(k>\alpha\). Hence \(r(\mathrm{SEP})=\infty\). The additive error on \(I_k\) is \(2k-2\), also unbounded: \(e(\mathrm{SEP})=\infty\).
-
If \(z(I)\ge 2\), then \(\frac{\mathrm{SEP}(I)}{z(I)}=\frac{n}{z(I)}\le\frac{n}{2}\). The bound depends on the instance through \(n\): a relative performance guarantee must be one constant \(\alpha\) valid for all the instances.
Exercise 34.4: Unbounded ratio of a greedy algorithm (1)
For the KP consider the algorithm \(\mathrm{GR}\): sort the items by non-increasing efficiency \(\frac{p_j}{w_j}\) (ties: smallest index) and insert each item, in this order, if it fits in the residual capacity. Consider the instance \(I_0\) with \(c=9\), \(p=(10,7,6,4)\), \(w=(5,4,3,3)\), and, for \(M\in\Z_{\ge 3}\), the instances \(I_M\) with \(c=M\) and two items: \(p_1=2\), \(w_1=1\) and \(p_2=M\), \(w_2=M\).
Questions
-
Apply \(\mathrm{GR}\) to \(I_0\), compute \(z(I_0)\) by enumeration, the performance ratio and the relative error.
-
Apply \(\mathrm{GR}\) to \(I_M\) and compute \(z(I_M)\), the performance ratio and the additive error for \(M=3,10,100\).
-
Is \(\mathrm{GR}\) an \(\alpha\)-approximation algorithm for some constant \(\alpha\)? Is it a \(\beta\)-additive approximation algorithm?
-
Which property of the instances \(I_M\) makes \(\mathrm{GR}\) fail?
Solution
We use the definitions (A1)–(A4) of the box at the beginning of the chapter.
-
The efficiencies are \(2\), \(\frac{7}{4}\), \(2\), \(\frac{4}{3}\): the order is \((1,3,2,4)\). \(\mathrm{GR}\) inserts items \(1\), \(3\) and gets \(\mathrm{GR}(I_0)=16\). Enumeration gives \(z(I_0)=17\) (items \(\{1,2\}\)). The ratio is \(\frac{17}{16}\) and the relative error is \(\frac{17-16}{17}=\frac{1}{17}\).
-
Item \(1\) has efficiency \(2\) and item \(2\) has efficiency \(1\): \(\mathrm{GR}\) inserts item \(1\), and then item \(2\) does not fit in the residual capacity \(M-1\). Hence \(\mathrm{GR}(I_M)=2\), while item \(2\) alone gives \(z(I_M)=M\):
\(M\) \(\mathrm{GR}(I_M)\) \(z(I_M)\) ratio additive error \(3\) \(2\) \(3\) \(\frac{3}{2}\) \(1\) \(10\) \(2\) \(10\) \(5\) \(8\) \(100\) \(2\) \(100\) \(50\) \(98\) -
The ratio \(\frac{M}{2}\) grows without limit, so no constant \(\alpha\) works and \(r(\mathrm{GR})=\infty\). The additive error \(M-2\) is also unbounded: \(e(\mathrm{GR})=\infty\).
-
The efficient item is small and blocks the large item, whose profit is almost all the optimal value: the order by efficiency ignores how much profit an item brings in absolute terms.
Exercise 34.5: Approximation schemes (1)
An approximation scheme \(\{\mathscr{A}_\varepsilon\}_{\varepsilon\in(0,1)}\) is run on some instances. The table gives the type of problem, the accuracy parameter \(\varepsilon\), the optimal value and the value returned:
| case | problem | \(\varepsilon\) | \(z(I)\) | \(\mathscr{A}_\varepsilon(I)\) |
|---|---|---|---|---|
| (1) | minimization | \(\frac{1}{10}\) | \(100\) | \(108\) |
| (2) | minimization | \(\frac{1}{10}\) | \(60\) | \(67\) |
| (3) | maximization | \(\frac{1}{5}\) | \(50\) | \(41\) |
| (4) | maximization | \(\frac{1}{5}\) | \(50\) | \(38\) |
Questions
-
For each case, compute the relative error and decide whether the value is compatible with the definition of an approximation scheme.
-
Translate \(\varepsilon=\frac{1}{4}\) into a relative performance guarantee, for a minimization and for a maximization problem. What is the accuracy?
-
A scheme for a maximization problem must be a \(\frac{5}{4}\)-approximation algorithm. Which value of \(\varepsilon\) is needed?
-
Classify the following running times of an approximation scheme on instances of size \(n\): \(O(n^{1/\varepsilon})\), \(O(n^{3}/\varepsilon)\), \(O(n\,2^{1/\varepsilon})\), \(O(n^{2}/\varepsilon^{2})\), \(O(2^{n}/\varepsilon)\).
Solution
-
-
(1) \(\frac{108-100}{100}=\frac{2}{25}\) \(\le\) \(\frac{1}{10}\): compatible.
-
(2) \(\frac{67-60}{60}=\frac{7}{60}\) \(>\) \(\frac{1}{10}\): not compatible, the scheme is wrong on this instance.
-
(3) \(\frac{50-41}{50}=\frac{9}{50}\) \(\le\) \(\frac{1}{5}\): compatible.
-
(4) \(\frac{50-38}{50}=\frac{6}{25}\) \(>\) \(\frac{1}{5}\): not compatible, the scheme is wrong on this instance.
-
-
For a minimization problem \(\mathscr{A}_\varepsilon(I)\le(1+\varepsilon)\,z(I)\), so the guarantee is \(1+\frac{1}{4}=\frac{5}{4}\). For a maximization problem \(\mathscr{A}_\varepsilon(I)\ge(1-\varepsilon)\,z(I)\), so the guarantee is \(\frac{1}{1-\varepsilon}=\frac{4}{3}\). The accuracy is \(\frac{1}{\varepsilon}=4\).
-
We need \(\frac{1}{1-\varepsilon}\le\frac{5}{4}\), that is \(1-\varepsilon\ge\frac{4}{5}\) and \(\varepsilon\le\frac{1}{5}\): any \(\varepsilon\le\frac{1}{5}\) works, and \(\varepsilon=\frac{1}{5}\) is the largest one.
-
-
\(O(n^{1/\varepsilon})\): PTAS, not FPTAS.
-
\(O(n^{3}/\varepsilon)\): FPTAS.
-
\(O(n\,2^{1/\varepsilon})\): PTAS, not FPTAS.
-
\(O(n^{2}/\varepsilon^{2})\): FPTAS.
-
\(O(2^{n}/\varepsilon)\): not a PTAS.
A PTAS needs a polynomial in \(n\) for every fixed \(\varepsilon\); an FPTAS needs a polynomial in both \(n\) and \(\frac{1}{\varepsilon}\). The terms \(n^{1/\varepsilon}\) and \(2^{1/\varepsilon}\) are not polynomial in \(\frac{1}{\varepsilon}\), and \(2^n\) is not polynomial in \(n\).
-